WASHINGTON, DC 20242 · DC — Ward 6
Building permit — civil plans
Construction of a temporary crossover lane from 395 SB to 395 SB HOV and construction of a staging area adjacent to 395/WMATA bridge pier
Applicant: PAUL DOLAN · Owner: UNITED STATES
Building permit — civil plans
CFA / H Long Bridge North (LBN) - Package MD4: Yard 7 includes establishing a contractor laydown area for the construction of the trestle across the Washington Channel, and to support the construction needs of the temporary and permanent pedestrian bridges in addition to the Maine Avenue CSX bridge. After the trestle connection is made, this will serve as the main construction access point for these activities.
Applicant: PAIGE BUCKLESS · Owner: UNITED STATES OF AMERICA
Building permit — civil plans
CFA / H Long Bridge North (LBN ) - Package MD6: Yard 1 & Yard 2 includes establishing two contractor laydown yards: Yard 1 on NPS Lot C and Yard 2 on NPS Lot B adjacent to I-395. Work activities include installing a driveway entrance for Yard 1, boundary fencing for both yards, and a temporary drainage system for Yard 1 with associated ESC measures for both yards throughout construction. Yard 1 will also be graded to accommodate a stabilized crane mat.
Applicant: PAIGE BUCKLESS · Owner: UNITED STATES OF AMERICA
Published by the District as assessment data, separately from the permit record above, and current as of the District’s own assessment cycle rather than today. An assessment can lag construction by a cycle, so a property with a recently issued permit may still be assessed as it was before the work. Owner details are published by the jurisdiction but are deliberately not shown here.
These are the permits published by the jurisdictions listed above. A project usually depends on approvals from other agencies that publish nothing machine-readable — a forest conservation exemption, a well completion report, a sediment control or grading plan, a utility connection, a homeowners’ association sign-off. Their absence here is not evidence they were not required, and the gaps between the dates above are usually where they happened. Rows labelled “Issued” are ISSUED permits — Washington DC publishes an issue date and no project valuation at all. Records are grouped by normalised address text, so the same property may also appear upstream under a different spelling. Verify scope, dates, and contractor information with the issuing jurisdiction before bidding, quoting, or performing work.