WASHINGTON, DC 20052 · DC — Ward 2
Building permit — electrical
Owner: GEORGE WASHINGTON UNIVERSITY
Building permit — solar system
HISTORIC INSTALLATION OF NEW PV SYSTEM 183 MODULES - 108.885 kW DC, 100.000 kW AC SYSTEM SIZE GELMAN LIBRARY BUILDING- GEORGE WASHINGTON UNIVERSITY
Applicant: KIM PREDDIE · Owner: GEORGE WASHINGTON UNIVERSITY
Building permit — plumbing and gas
Owner: GEORGE WASHINGTON UNIVERSITY
Building permit — mechanical
Owner: GEORGE WASHINGTON UNIVERSITY
Building permit — plumbing and gas
Owner: GEORGE WASHINGTON UNIVERSITY
Building permit — electrical
Owner: GEORGE WASHINGTON UNIVERSITY
Building permit — electrical
Owner: GEORGE WASHINGTON UNIVERSITY
Building permit — alteration and repair
HISTORIC Revision to previously apporved permit B2505975. Replacement of existing building primary HVAC equipment and control devices to meet current code. Project includes supplemental HVAC system to support new special collection room in the first floor.
Applicant: MANDY LEUNG · Owner: GEORGE WASHINGTON UNIVERSITY
Published by the District as assessment data, separately from the permit record above, and current as of the District’s own assessment cycle rather than today. An assessment can lag construction by a cycle, so a property with a recently issued permit may still be assessed as it was before the work. Owner details are published by the jurisdiction but are deliberately not shown here.
These are the permits published by the jurisdictions listed above. A project usually depends on approvals from other agencies that publish nothing machine-readable — a forest conservation exemption, a well completion report, a sediment control or grading plan, a utility connection, a homeowners’ association sign-off. Their absence here is not evidence they were not required, and the gaps between the dates above are usually where they happened. Rows labelled “Issued” are ISSUED permits — Washington DC publishes an issue date and no project valuation at all. Records are grouped by normalised address text, so the same property may also appear upstream under a different spelling. Verify scope, dates, and contractor information with the issuing jurisdiction before bidding, quoting, or performing work.